Our process for estimation, in one place

For a while, the handling of estimation was improvised. Now there's a fixed order, and this post walks through it.

Context

A look back at how much time tasks really took, next to the original guess, remains the best way we know to improve, and it stays blame-free. The scope, not speed, should be our first lever if the deadline is fixed.

How We Do It

  1. 01

    Split the Work First

    A project gets split into pieces of no more than three days each before anyone puts a number on it; a piece that can't be split often hides an unknown that needs a short investigation first.

  2. 02

    Give a Range

    Each estimate is a range - a likely figure and the bad-week one - and the width of the range tells how much we still don't know yet.

  3. 03

    Compare with What Happened

    Once the work ships, the real time goes beside the estimate in the planning sheet; once a quarter the team looks at the gap between the two and adjusts the next ranges.

If no one can say how long something will be, a time-boxed experiment of a day or two gives an honest estimate cheaper than guessing.